Steel and Tube Warehouse Auckland

Steel and Tube Warehouse, Auckland

Project Background

This project involves Steel and Tubes new roofing and office block

The warehouse design included 3No 5 tonne gantry cranes plus a 3 tonne gantry crane. A large entry canopy was also designed using composite dual columns.

The main ware house slab and the yard slabs were both designed as jointless fibre reinforced slabs.

Solutions Provided

Manu Withers, acting as Project Engineers and Lead Structural Engineer, while working for MSC Consulting Group Ltd provided the following services and solutions on this project:

  • Tender Design Documentation
  • Project Management, Value Engineering
  • Design Team Liaison.
  • Structural design
  • Construction monitoring
  • Client and Contractor liaison

Steel__Tube.jpg